Regulatory and Operational Impacts on Indonesia’s Shipbuilding Costs
Main Article Content
Abstract
Regulatory and Operational Impacts on Indonesia’s Shipbuilding Costs: This study aims to quantify the impact of regulatory and operational delays on shipbuilding costs in Indonesia, a maritime nation undergoing rapid infrastructure modernization. Grounded in the theoretical frameworks of institutional economics and project risk management, the research investigates how permit duration and project delays affect the financial performance of nationally significant vessel construction projects. Employing a quantitative approach, data from 14 real-world shipbuilding projects including patrol boats, offshore patrol vessels (OPVs), tankers, and submarines were analyzed. Key variables comprised total project cost (in billion IDR), permit time (months), and project delay duration (weeks). Descriptive statistics, Pearson correlations, and multiple linear regression were performed, followed by robust regression and outlier diagnostics (Cook’s Distance and VIF analysis) to ensure model reliability. The results reveal that project delays significantly increase total costs (p < 0.001), whereas permit duration exhibits a negative but context-dependent relationship. The model explains 68% of cost variation (R² = 0.68), with multicollinearity between permit time and delays (r = 0.94) indicating the need for cautious interpretation. Robust regression and diagnostic tests confirm the influence of high-cost defense projects as outliers. These findings provide actionable insights for maritime infrastructure policy, highlighting the need to streamline permit procedures, enhance inter-agency coordination, and mitigate project execution delays. This research contributes novel empirical evidence from real project data and applies advanced diagnostic techniques, addressing a critical gap in Southeast Asian maritime economics literature.
Downloads
Article Details
Section

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.
Authors who publish with this journal agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Effect of Open Access).

Jurnal Penelitian Transportasi Laut by Puslitbang Transportasi Laut, SDP is licensed under a CC BY-NC-SA
Based on a work at https://ojs.balitbanghub.dephub.go.id/index.php/jurnallaut/
References
[1] UNCTAD, Review of Maritime Transport 2024, United Nations, 2024. https://unctad.org/publication/review-maritime-transport-2024
[2] International Maritime Organization (IMO), IMO Greenhouse Gas Strategy: 2023 Revised Edition. London: IMO Publishing, 2023.
[3] World Bank, Maritime Transport and Infrastructure Modernization in East Asia and the Pacific. Washington, DC: World Bank Group, 2024.
[4] Shipbuilding – A Numbers Game,” Asian Military Review, May 2021. [Online]. Available: https://www.asianmilitaryreview.com/2021/05/shipbuilding-a-numbers-game
[5] H. Vaagen and T. K. Andersen, “Lean and flexible project delivery in engineer-to-order and construction projects,” Applied Sciences, vol. 11, no. 19, p. 9287, 2021, doi: 10.3390/app11199287.
[6] J. Zhu and Y. Lin, “Fuzzy DEMATEL–QFD for designing supply chain of shipbuilding materials,” Journal of Marine Science and Engineering, vol. 9, no. 10, p. 1106, 2021, doi: 10.3390/jmse9101106.
[7] J. Bell-James, D. Morris, J. A. Fitzsimons, and K. R. Brown, “The permitting process for marine and coastal restoration: Practitioner experiences and legal challenges,” Conservation Science and Practice, vol. 5, no. 6, e13050, 2023, doi: 10.1111/csp2.13050.
[8] A. Migone, “Failure where alignment is lacking: Type 26 frigate and Canadian surface combatant,” in Procuring Advanced Military Platforms and Systems. Cham: Springer, 2023, pp. 41–67, doi: 10.1007/978-3-031-25689-9_3.
[9] A. C. Alves, “The cost of missions: Lessons from Brazilian shipbuilding,” in Industrial Strategy and Development in Latin America. Cham: Springer, 2024, pp. 203–224, doi: 10.1007/978-3-031-49196-2_10.
[10] D. Susanto and S. Raharjo, “Bureaucratic fragmentation and shipbuilding delays in Indonesia,” Journal of Maritime Policy Studies, vol. 9, no. 2, pp. 77–89, 2022, doi: 10.1016/j.marpol.2022.105678.
[11] T. Wibowo, “Qualitative assessment of project delays in maritime infrastructure,” International Journal of Maritime Economics, vol. 11, no. 3, pp. 233–244, 2021, doi: 10.1016/j.ijme.2021.05.004.
[12] A. Álvarez-Pozo, M. Parma-García, M. Ortiz-Marcos, R. Bautista, and A. Atanes-Sánchez, “Analysis of causes of delays and cost overruns in turnkey industrial projects,” Sustainability, vol. 16, no. 4, p. 1449, 2024, doi: 10.3390/su16041449.
[13] W. Xie, X. Li, and Q. Zhao, “Critical factors influencing cost overrun in construction projects,” Buildings, vol. 12, no. 11, p. 2028, 2022, doi: 10.3390/buildings12112028.
[14] M. Welde and S. Lædre, “Evaluating defence projects: Success may be more than cost, schedule, and performance,” Impact Assessment and Project Appraisal, vol. 43, no. 5, pp. 534–548, 2025, doi: 10.1080/14702436.2025.2461459.
[15] E. F. Woodhouse, “The distributive politics of privately financed infrastructure,” Governance, vol. 37, no. 4, pp. 1175–1196, 2024, doi: 10.1111/gove.12824.
[16] A. Setiawan, “Regulatory challenges and cost efficiency in Indonesia’s shipbuilding,” SSRN Preprint, 2025, doi: 10.2139/ssrn.5167627.
[17] I. Baroroh and B. Ma’ruf, “Supply chain mitigation for shipbuilding in Indonesia shipyard by using Bayesian network,” Transactions on Maritime Science, vol. 14, no. 3, pp. 245–258, 2025, doi: 10.7225/toms.14.3.245.
[18] U.S. Government Accountability Office, Navy Shipbuilding: A Generational Imperative for Systemic Reform, GAO Report GAO-25-108136, 2025. [Online]. Available: https://www.gao.gov/products/gao-25-108136
[19] Y. Zhang and J. Chen, “Shipbuilding 4.0 and performance metrics,” Ocean Engineering, vol. 276, p. 115612, 2023, doi: 10.1016/j.oceaneng.2023.115612.
[20] P. Centobelli, R. Cerchione, and E. Esposito, “Supply chain resilience in maritime manufacturing,” Technological Forecasting and Social Change, vol. 188, p. 122320, 2023, doi: 10.1016/j.techfore.2023.122320.
[21] M. Mauro and R. de Mesquita, “Digital twin governance in industrial projects,” Computers in Industry, vol. 152, p. 103823, 2023, doi: 10.1016/j.compind.2023.103823.
[22] A. Frank, S. Oliveira, and J. Costa, “Institutional inertia in public procurement,” Public Administration Review, vol. 85, no. 2, pp. 372–385, 2025, doi: 10.1111/puar.13526.
[23] Q. Li, W. Jiang, and H. Zhang, “Optimization of block flow-line scheduling in shipyards,” Automation in Construction, vol. 165, p. 105050, 2024, doi: 10.1016/j.autcon.2024.105050.
[24] H. Liu, Z. Zhang, and C. Hu, “Hybrid scheduling optimization in smart shipbuilding,” Advanced Engineering Informatics, vol. 54, p. 102150, 2022, doi: 10.1016/j.aei.2022.102150.
[25] S. Choi and Y. Seo, “Vision-based progress monitoring for shipbuilding,” Automation in Construction, vol. 120, p. 103427, 2020, doi: 10.1016/j.autcon.2020.103427.
[26] D. Ma and J. Lee, “Deep learning for defect detection in marine coating processes,” Journal of Manufacturing Systems, vol. 72, pp. 141–152, 2022, doi: 10.1016/j.jmsy.2022.01.012.
[27] J. Yi, W. Tang, and P. Zhou, “AI-orchestrated smart factory for shipbuilding,” Journal of Intelligent Manufacturing, vol. 34, pp. 1853–1870, 2023, doi: 10.1007/s10845-023-02017-5.
[28] E. Apilioğulları, “Integration of ISA-95 model in maritime manufacturing,” Journal of Manufacturing Technology Management, vol. 33, no. 8, pp. 1456–1475, 2022, doi: 10.1108/JMTM-09-2021-0378.
[29] K. Park, J. Yoon, and S. Cho, “Virtual compliance training for industrial safety in shipyards,” Safety Science, vol. 168, p. 106961, 2023, doi: 10.1016/j.ssci.2023.106961.
[30] A. Setiawan, “Institutional determinants of shipbuilding delays,” Marine Policy, vol. 162, p. 105547, 2025, doi: 10.1016/j.marpol.2025.105547.
[31] R. Huang, S. Wang, and K. He, “Principal component decomposition for project cost forecasting,” Engineering, Construction and Architectural Management, vol. 32, no. 3, pp. 623–640, 2025, doi: 10.1108/ECAM-04-2024-0315.
[32] N. Wang, H. Liu, and J. Li, “Dynamic GMM estimation for infrastructure cost modeling,” Economic Modelling, vol. 124, p. 106546, 2025, doi: 10.1016/j.econmod.2025.106546.
[33] M. Álvarez, J. Dávila, and L. Rivas, “Cross-sectoral learning from naval procurement delays,” Journal of Infrastructure Systems, vol. 31, no. 2, p. 04023011, 2025, doi: 10.1061/JISEB3.04023011.
[34] European Commission, EU Shipbuilding and Innovation Report 2025. Brussels: DG MOVE, 2025. [Online]. Available: https://transport.ec.europa.eu